Aquativity Progress Update


The working party on 26 January was a big success, with a huge amount of work completed - see the slide show. Many thanks to all who turned up to help.

Since the weekend, we've got more boarding, more electrics and in particular, the plasterers have moved in - the hall is plastered, with landing and stairs well underway. We are seeing really rapid progress at the moment - rushing towards completion.

Next steps include finishing the heating system in the hall then putting the panels up you can see are missing above the windows, putting downlighters into those panels to complement the main central lights, fitting door liners and doors, plumbing and painting, as well as finishing off the side rooms ready for plastering. We still need help on Thursay evenings - and a new date for your diary = Saturday 16th February - please come along.